ANALISIS PROYEK PEMBANGUNAN KANTOR DENGAN MENGGUNAKAN C.P.M. DI PT KASOEM HEARING CENTRE

RUHIMAT RUHIMAT, BUDI SUMARTONO, HARI MOEKTIWIBOWO

Sari


PT. Kasoem Hearing Center is one of companies focusing on hearing aid and optic which is located in Jl.Cikini Raya no.18 Jakarta Pusat. A company often get a problem when finishing the project because it is not appropriate with the time agreed before. Therefore, analysis of project time optimalization is needed to know how long the project is finished, and to find out existence of time acceleration possibility of the project implementation by using CPM. Steps in analyzing of PT. Kasoem Hearing Centre office development project are: deciding stages of activity, changing of chart, track lane, critical path, calculating the cost, accelerating of processing time, and counting the project using CPM. Forms of job network of PT. Kasoem Hearing Centre Office Project are: Preparation & Destruction Job – Earthworks, excavation, fill the ground, installation – Structural work & amp; reinforced concrete – Wall work – Roof job – Electrical installation work A – Floor job A – Ceiling job A – Door and window job A – Finishing, painting, etc. B=A-B-C-D-F-H-L-N-O-Q-R-S-U-V (critical path), with optimal time duration of Office development project is 159 days from 174 days normal time. Based on researching result, researcher gives suggestion as follows: The Project Team should use CPM in implementing Office development project. Because the faster completion time of Office development project, then the office also can be operated to support activity needs and employee operational.

Keywords : Project, CPM, Project Time, Project Costs


Teks Lengkap:

PDF

Referensi


Alan D ORR, TH 2012. Manajemen

Proyek lanjutan. PT. Indeks Jakarta

Ali,Tubagus Haedar, 1986.

Prinsip-prinsip network planning.

PT.Gramedia Jakarta.

Anggara, H. 2005. Perencanaan dan

Pengendalian Proyek dengan

Metode PERT-CPM: Studi Kasus Fly

Over Ahmad Yani, Karawang. Journal

the Winners, Vol. 6, No.2: 155-174.

Dannyanti, E. 2010. Optimalisasi

Pelaksanaan Proyek dengan Metode

Pert dan CPM (Studi Kasus Twin

Tower Building Pascasarjana Undip).

Penelitian, FT Undip. Semarang.

Dimyati,Hamdan, dan Nurjaman, Kadar,

Manajemen Proyek. Pustaka

Setia Bandung.

Gray, C. Simanjuntak, P., Lien K.S

Mspaitella, P.F.L., Varley,R.C.G. 2007.

Pengantar Evaluasi Proyek.

Gramedia Pustaka utama. Jakarta

Levin Richard I. & Kirpatrick Charles A.

Perentjanaan dan pengawasan

dengan PERT dan CPM. Bhrata.

Jakarta.

Render, Barry & jay Heizer. 2004.

Manajemen operasi. Salemba empat.

Jakarta.

Schwalbe, Kathy. 2004. Imformation

Technology Project Management.

Edisi Ke-4. Course Technology, Inc.

Boston.

Siswanto. 2007. Operation Research

Jilid II. Erlangga. Jakarta.

Soeharto, I. 1999. Manajemen

Konstruksi dari konseptual Hingga

Operasional. Erlangga. Jakarta.

Subagya. 2000. Analisi Manajemen

Proyek. Graha Pena. Bekasi.

Maryati, MC. 2008. Manajemen

Perkantoran Efektif. Yogyakarta : YKPN




DOI: https://doi.org/10.35968/jtin.v8i2.798

Refbacks

  • Saat ini tidak ada refbacks.


Indexed by: